Construction Update - October 4, 2019

Residents of High Street and Antrim Street should be aware construction crews will be working Saturday, October 5th.

 

The Town of Carleton Place together with AECON would like to inform residents of the following activities planned for the coming days:

 

On High Street, AECON’s crews will be completing the process to deepen and replace the storm sewer between Moffatt Street and Joseph Street in the next few days.   AECON crews will also continue to repair services as necessary.  Crews will carry on with the road excavation throughout the active construction zone.

 

In the next few days, crews will be replacing catch basins and leads and begin repairing services where required on Antrim Street.  AECON will begin the process to remove concrete sidewalks and asphalt in preparation for road excavation.

 

AECON will have a crew on Mary Street next week to replace a catch basin and its lead.

 

AECON will be informing the impacted residents directly, if and when, their individual service connections could be affected. 

 

With children travelling to and from school, the Town of Carleton Place and AECON are urging parents to avoid using the construction areas as your route to and from school and to keep children away from the construction zones.  The appeal of construction vehicles is tempting to curious children but for safety reasons we are requesting children stay away from the construction zones.

 

AECON and the Town of Carleton Place request your assistance in ensuring safe and efficient work zones.  However, should residents be travelling within the construction zones, we urge you to proceed with caution and follow the directions provided by the Traffic Control persons and posted construction signage.

 

If a resident has any questions or concerns regarding these activities, please call (613) 257-2253.