Arena Construction Project Update - August 26th, 2021

Photo of one of the new Arena Dressing ROomsPartial occupancy of the two (2) most easterly change rooms was received on August 9th, 2021 in time for the opening of Arena No. 1.  Some finishing work on all new change rooms still needs to be completed.  Work will be completed entirely on the two (2) most westerly change rooms first in the next few weeks followed by the remaining works on the easterly change rooms.  

The installation of the front window glazing and slider door system has commenced and will be completed shortly.

The installation of the sidewalk along Begley Street was completed last week.

The grinding of the lobby floor will be completed this week in preparation for installation of new rubbing matting which is expected to commence mid-September. Following the installation of rubber matting, the remaining items will be completed to finalize the lobby area.

Touch-ups and addressing deficiency items will occur simultaneously and following flooring installation.

Together, Tal-Co Building Innovations Ltd. and the Town of Carleton Place would like to ask for everyone’s help in ensuring safe and efficient work zones.  Should residents be travelling within the construction zone we urge you to proceed with caution.

We ask for everyone’s patience and cooperation as this construction project proceeds, however, should a member of the public have any concerns or questions of a general nature, please contact the Recreation and Culture Office at 613-257-1690.