Central Bridge Construction Update - March 31, 2022

Central Bridge Reconstruction

The essential rehabilitation of the existing piers is continuing.  The barge with the drill rig has been relocated to the south pier and drilling will commence in the coming days to install micro piles to provide additional strength to support the beams for the new bridge structure. 

Removal operations are continuing with both abutments. 

Bridge Street Reconstruction

For residents wondering about the status of the reconstruction of Bridge Street, please know Louis Bray is working very closely with Town staff to finalize the schedule.  The start date will be Monday, May 2nd.

Should you have any questions or concerns regarding the Central Bridge or Bridge Street projects, please call (613) 257-2253 or email to dyoung@carletonplace.ca