Construction Update - August 12, 2020

The Town of Carleton Place would like to advise our residents of the following activities for the coming week:

Patterson Cres.

Now that the top lift of asphalt has been completed, crews will be on Patterson Crescent replacing topsoil behind sections where concrete repairs have been completed.

High Street

Cavanagh’s crews will be continuing with the installation of catch basins and storm leads in identified locations.  Crews will also be installing a new fire hydrant which will require water to be turned off for an extended period of time.  Residents impacted by the shutdown will be notified by Cavanagh Construction.  Crews will also be removing portions of the concrete curb and removing asphalt in preparation for road excavation. 

Together, Thomas Cavanagh Construction and the Town of Carleton Place would like to ask for everyone’s help in ensuring safe and efficient work zones.  We would like to encourage residents to avoid the construction zones, however, should residents be travelling within the construction zones we urge you to proceed with caution and follow the directions provided by the Traffic Control persons and posted construction signage.

We ask for everyone’s patience and cooperation during the construction season, however, should a member of the public have any concerns or questions of a general nature, please contact the Public Works Office at 613-257-2253.