The Public Works Department would like to remind residents that weather, staffing, and supply of materials can impact our construction schedules. The following activities are anticipated for the upcoming week:

Thomas Street (Townline Road to Bridge Street)

Concrete crews are scheduled to return to Thomas Street next week to begin the process of installing new curbs and repairing broken sidewalk panels. Residents should be reminded Thomas Street remains closed between McKenzie Street and Bridge Street.

Joseph Street Pumping Station

Steady progress is being made with the electrical installations between the wet well and the control building. A new natural gas service has been installed to power the backup generator.

Should you have any questions or concerns regarding any of our projects, please call (613) 257-2253.