facebook icon  Twitter Icon

Live

Carleton Place Logo

What's New

Bridge Street On-Street Parking Restrictions to Facilitate Asphalt The Town of Carleton Place Public Works Department would like to advise residents we have now reached the most critical part of the revitalization of Bridge Street.  Under the direction of Louis W. Bray Construction, Thomas Cavanagh Construction will be moving onto Bridge Street tomorrow to begin preparing the granular base on Bridge Street for base course asphalt later next week. Sidewalk work also continues on the east side of Bridge Street.  For all contractors to work as safely and efficiently as possible, on-street parking on Bridge Street will not be permitted until after the base
full story
Construction Update – September 22nd, 2022 The Town of Carleton Place Public Works Department would like to remind residents that weather conditions and supply of materials have the potential to impact construction schedules and objectives for the week ahead.  Activities anticipated for the upcoming week include the following: Bridge Street Revitalization The last couple of weeks have seen significant progress achieved on Bridge Street. Concrete sidewalks are near completion and the next stage of the concrete work will see the decorative stamped concrete installed along the curbs and around landscape areas. Work is progressing
full story
Construction Update – September 15th, 2022 The Town of Carleton Place Public Works Department would like to remind residents that weather conditions and supply of materials can have the potential to impact construction schedules and objectives for the week ahead.  Activities anticipated for the upcoming week include the following: Bridge Street Revitalization Concrete crews will be continuing with the construction of the raised planter bases and concrete sidewalk installations on the east side of Bridge Street. Louis Bray’s staff will be reinstating as much on-street parking as possible for the weekend, but with multiple
full story
Construction Update - September 8th, 2022 The Town of Carleton Place Public Works Department would like to remind residents that weather conditions can potentially impact construction schedules and objectives for the week ahead.  Activities anticipated for the week ahead include the following: Bridge Street Revitalization Now that concrete curbs have been installed, the raised planter bases and concrete sidewalk installation on the east side of Bridge Street will be commencing. Asphalt removals are underway and are likely to continue into next week. Louis Bray staff will be reinstating as much on-street parking as possible for
full story
Other News
National Forest Week
Temporary closure of CPDMH Emergency Department
September 1st Construction Update
Tornado Warning from Environment and Climate Change Canada:
Labour Day Waste Collection
Hydro One Outage
Construction Update – August 25th, 2022
Construction Update – August 18th, 2022
Traffic Interruptions Planned for Bridge, Allan, and Mill Streets
Heat Protection
Show All