Municipal Infrastructure Construction Projects
The Town of Carleton Place is responsible for approximately 65 kilometers of road ways, underground infrastructure, streetlights, sidewalks, etc. and periodically municipal infrastructure requires maintenance or replacement. The Town recognizes these assets are costly to replace so we do our utmost to ensure these assets are kept in a state of good repair.
The Town of Carleton Place is committed to maintaining communication with our residents regarding our construction projects. If you have questions about any Public Works construction activity please contact the Public Works office at (613) 257-2253.
PW-2026-02
Frank Street, Emily to River- Asphalt and granular removals, installation of mountable curb, iron adjustments, reinstatement of granular bedding and asphalt pavement.
Lake Avenue West, O’Donovan to Boat Launch – Asphalt and granular removals, culvert removal, repairs to sidewalk and curb sections, installation of new sidewalks and curbs, installation of a catch basin and storm pipe, Iron adjustments and reinstatement of granular bedding and asphalt pavement.
Sarah Street, Arthur to Morris – Asphalt and granular removals, repairs to curb sections, Iron adjustments, and reinstatement of Granular bedding and asphalt pavement.
Sarah Street, Lake Ave West to Woodward – Asphalt and Granular Removals, repairs to sidewalk and curb sections, Iron adjustments and reinstatement of Granular bedding and asphalt pavement.
Napoleon Street, Wilson to Woodward – Asphalt and Granular Removals, repairs to sidewalks and curb sections, replacement of watermain, iron adjustments and reinstatement of Granular bedding and asphalt pavement.
Overlay
Joseph Street, High to Townline Rd – Asphalt grinding, sidewalk section repairs, iron adjustments and reinstatement of asphalt pavement.
James Street, Bell to Townline Rd – Asphalt grinding, sidewalk section repairs, iron adjustments, and reinstatement of asphalt pavement.
Wellington Queen to Park- Asphalt grinding, Sidewalk section repairs, iron adjustments, and reinstatement of asphalt pavement.
PW-2024-01
Pumping Stations:
Princess Pumping Station:
Description: Rehabilitation of the existing pumping station including new manhole, wet well insert, new pumps, piping and instrumentation, new natural gas generator, rehabilitation of the existing building.
Project Status: Expected to be completed in second quarter 2026.
Findlay Pumping Station:
Description: Rehabilitation of the existing pumping station including replacement of existing building, wet well insert, new pumps, piping and instrumentation, new natural gas generator.
Project Status: Expected to be completed in second quarter 2026.