Carleton Place logo in white

Construction Update

The Town of Carleton Place reminds residents that weather, staffing, and the supply of materials can affect the construction schedule.

This Week’s Construction Updates

The following table summarizes planned activity at each active construction site this week.

Project / LocationUpdate
McNeely Avenue Sanitary Sewer Upsizing ProjectCavanagh Construction will remove a hydrant this week, then begin sewer removal and replacement starting Wednesday, July 2. Work is in the easement directly west of Hooper Street, behind Canadian Tire. By-pass pumping will be set up adjacent to the Canadian Tire and Independent Grocer parking lots.
Bennett StreetTop-lift asphalt paving is planned for the upcoming week.
Duncan StreetTop-lift asphalt paving is planned for the upcoming week.
Ann and Brown StreetTop-lift asphalt paving is planned for the upcoming week.
Princess Street Pumping StationCrews will locate the forcemain and install a new sanitary sewer manhole.
Findlay Avenue Sanitary Pumping StationExcavation continues to expose the forcemain for by-pass pump installation.

Stay Safe Near Construction Zones

For everyone’s safety, the Town of Carleton Place and its contractors ask residents to find alternate routes around active construction zones. If you’re unable to find an alternate route, please reduce your speed and follow the directions provided by flag crews and posted signage. Our goal is for everyone to get home safely at the end of each day.

Questions?

Contact the Public Works Office at 613-257-2253 with any questions about these projects.