Construction activities anticipated for the upcoming week include the following.
Active construction locations
| Location | Update |
|---|---|
| Public Works Yard – 97 Franklin Street | Foundations for both buildings have been backfilled, and granulars for the floors are being placed. |
| Frank Street (Emily Street to the Mississippi River) | All road work is complete. Driveway reinstatement and paving will take place in early August. |
| Napoleon Street (Wilson Street to Woodward Street) | Watermain commissioning continues until July 28. Roadwork will begin July 28, once commissioning is complete. |
| Sarah Street (Lake Avenue to Woodward Street) | Road construction and concrete replacement are ongoing. |
| Sarah Street (Arthur Street to Morris Street) | Road construction and concrete replacement are ongoing. |
| College Street (Victoria Street to Bridge Street) | Roadway removal and concrete work will continue over the next week. |
| Rosamond Street OVRT crossing | Roadway removal will begin July 31. |
Stay safe near construction zones
Please use alternative routes to avoid active construction zones where possible, and reduce your speed if you can’t avoid an affected area. Weather, staffing, and material availability can affect the construction schedule.
Landscaping reinstatement on completed streets is postponed until September because of summer heat conditions.
Contact us
For questions about construction activity, call Public Works at 613-257-2253.
Contact information
- Phone: 613-257-6200
- Emergency: 613-257-2253
- Email: info@carletonplace.ca
- Address: 175 Bridge Street, Carleton Place, ON K7C 2V8