The Town of Carleton Place would like to remind residents that weather, staffing, and supply of materials can impact the construction schedule. Activities anticipated for the upcoming week include the following:
Water Treatment Plant & Wastewater Treatment Plant Expansions
Work is continuing on the construction of the wet well for the new headworks building at the Wastewater Treatment Plant, along with rock excavation and blasting for the new buildings and pipe trenches. The new forcemains and watermains are in the process of being installed at the Water Treatment Plant.
Captain A. Roy Brown Extension and McEachen Drive Construction
Crews will be on site installing utilities for streetlights.
Charles Street
Crews will be paving top lift asphalt.
St. Paul Street
Crews will be paving top lift asphalt.
Findlay Avenue Pumping Station
Work is expected to resume this week on the forcemain and new building installations.
Industrial Avenue Pumping Station
Work continues on the new building and the installation of the internal components in the new wet well.
Princess Street Pumping Station
Work continues on the control panels within the existing building. The pads for the generator and gas meter will be poured once the electrical conduits have been installed.
For everyone’s safety, the Town of Carleton Place and its contractors would like to request that residents find alternative routes to avoid these active construction zones. If you are unable to find alternative routes around the construction, please reduce your speed and follow the directions provided by flag crews and/or any posted signage. Our goal is to ensure everyone is able to go home safely at the end of each day. Should you have any questions about any of our projects, please reach out to the Public Works Office at (613) 257-2253.