Municipal Infrastructure Construction Projects
The Town of Carleton Place is responsible for approximately 65 kilometers of road ways, underground infrastructure, streetlights, sidewalks, etc. and periodically municipal infrastructure requires maintenance or replacement. The Town recognizes these assets are costly to replace so we do our utmost to ensure these assets are kept in a state of good repair.
The Town of Carleton Place is committed to maintaining communication with our residents regarding our construction projects. If you have questions about any Public Works construction activity please contact the Public Works office at (613) 257-2253.
PW-2024-01
Project Status:
Contract has been awarded to Thomas Cavanagh Construction Limited (TCCL). Work is slated to begin on June 30th and the project is expected to be fully complete by mid-October. Proposed start dates at the various locations is as follows:
Nelson Street – starting week of June 16th
Overlay streets (Blair, Judson and Lemaistre) starting week of September 8th
Alexander Street – starting week of August 18th
Ramsay Street – starting week of June 23rd
Donald Street – starting week of June 30th
St Paul Street and Wilson Street – June 30th
Library Parking Lot and Moore House Parking Lot – starting week of September 15th
Please note that the preliminary schedule is subject to change and can be adversely impacted by weather conditions. Residents will receive letters from TCCL in advance of the work beginning on their street.
RECONSTRUCTION OF:
Donald Street – Road excavation, concrete curbs and paving.
Nelson Street West – Road excavation, watermain up sizing, concrete sidewalks, concrete curb repairs and paving.
Alexander Street – Road excavation, concrete curb repairs and paving.
Ramsay Street – Road excavation, concrete sidewalk, concrete curbs and paving.
St. Paul Street – Road excavation, concrete sidewalk, concrete curbs and paving.
Wilson Street – Road excavation, concrete sidewalk extension and repairs, concrete curbs and paving.
REHABILITATION OF:
Library Parking Lot – Asphalt replacement, granular reshaping and concrete curb repairs.
Moore Street Parking Lot – Asphalt replacement, granular reshaping and concrete curb repairs.
OVERLAY OF:
Blair Street – Asphalt grinding and paving, concrete sidewalk and curb repairs. Approximately 190m long x 8.5m width of road from Mississippi Road to Burgess Street.
Judson Street – Asphalt grinding and paving, concrete sidewalk and curb repairs. Approximately 300m long x 8.5m width of road from Mill Street to Albert Street.
Lemaistre Street – Asphalt grinding and paving, concrete sidewalk and curb repairs. Approximately 220m long x 8.5m width of road from Barker Street to Dunham Street.
Pumping Stations:
Princess Pumping Station:
Description: Rehabilitation of the existing pumping station including new manhole, wet well insert, new pumps, piping and instrumentation, new natural gas generator, rehabilitation of the existing building.
Project Status: Under contract negotiations with successful contractor
Findlay Pumping Station:
Description: Rehabilitation of the existing pumping station including replacement of existing building, wet well insert, new pumps, piping and instrumentation, new natural gas generator.
Project Status: Under contract negotiations with successful contractor
PW3-2022 – Joseph Street Pumping Station Rehabilitation
Project Update 2024:
Resolving deficiencies.
Project Description:
Rehabilitation of existing sanitary sewer pumping station which includes the replacement of the existing building, pumping equipment and instrumentation, & installation of new natural gas generator.
Contact Person for this Project:
Guy Bourgon
Email: gbourgon@carletonplace.ca
Tel: 613-257-6209