The Public Works Department would like to remind residents that weather, staffing, and supply of materials can impact the construction schedule. Activities anticipated for the upcoming week include the following:
Bennett Street
Crews will be reinstating the concrete curb where needed.
Duncan Street
Crews will be reinstating the concrete curb where needed.
Ann and Brown Street
Crews will be replacing the granular materials. Additionally, crews will be installing a new catch basin on Ann Street to assist with drainage.
Princess St. & Findlay Ave. Sanitary Pumping Stations
Black and McDonald Ltd. will be mobilizing to both sites next week and will begin setting up construction fencing around the perimeter of these sites to ensure safety.
Planned Hydro Outage
The Town of Carleton Place would like to advise residents and businesses of a planned power outage that is scheduled for Sunday, June 8th, 2025, from 7:00 a.m. to approximately 11:00 a.m. to allow Hydro One to install new equipment. The outage will affect Industrial Avenue and Smythe Road. Properties owners can contact Hydro One for more information.
For everyone’s safety, the Town of Carleton Place would like to request that residents find alternative routes to avoid these active constructions zones. If you cannot avoid these areas, please reduce your speed and follow the directions provided by flag crews and/or any posted signage. Our goal is to ensure everyone is able to go home safely at the end of each day. Should you have any questions about any of our projects, please reach out to the Public Works office at (613) 257-2253.