Weather, staffing, and the supply of materials can affect the construction schedule.
This Week’s Construction Updates
The following table summarizes progress at each active construction site for the week of November 20, 2025.
| Project / Location | Update |
|---|---|
| Water Treatment Plant and Wastewater Treatment Plant Expansions | Crews are pouring concrete for the wet well at the Wastewater Treatment Plant’s new headworks building and beginning base preparation for the Rotary Drum Thickener building. At the Water Treatment Plant, newly installed watermains will undergo testing and chlorination ahead of connections. |
| Captain A. Roy Brown Blvd. Extension and McEachen Drive | Road construction and utility installation work continues toward project completion. |
| Findlay Avenue Pumping Station | A natural gas road crossing will take place Monday and Tuesday of next week, requiring the closure of Findlay Avenue for this work. Detours will be in place. |
| Industrial Avenue Pumping Station | Control building roof installation is underway, followed by instrumentation pad installation. |
| Princess Street Pumping Station | Foundation pads for the new natural gas generator and gas meter will be poured. Roofing work is complete. |
Stay Safe Near Construction Zones
Residents are urged to use alternate routes around active construction zones. Anyone unable to do so should reduce speed and follow flag crew directions and posted signage.
Questions?
Contact the Public Works office at 613-257-2253.